Projects · Bahamas · 2020–2023
Baker's Bay Golf & Ocean Club
A hybrid plant on an island: engines, solar and storage working together to supply continuous power to a resort development in the Bahamas.
7MW
Capacity
Bahamas
2023
Year
2020–2023
150+GWh
Energy generated
Estimated to date
Design and construction as co-EPC partner
Scope
What was done
At Baker's Bay Golf & Ocean Club, the group took part as co-EPC partner in the design and construction of a 7 MW hybrid plant.
The plant combines three Jenbacher JMS420 engines with solar PV and a 3 MW / 3 MWh battery energy storage system (BESS). It is the direct precedent for GIS Power’s signature: solar and BESS as part of primary power.
Technical summary
- 3 Jenbacher JMS420 engines
- Solar PV
- 3 MW / 3 MWh BESS
- Project investment: USD 25 M
- co-EPC partner