Projects · Bahamas · 2020–2023

Baker's Bay Golf & Ocean Club

A hybrid plant on an island: engines, solar and storage working together to supply continuous power to a resort development in the Bahamas.

7MW

Capacity

Bahamas

2023

Year

2020–2023

150+GWh

Energy generated

Estimated to date

Design and construction as co-EPC partner

Scope

What was done

At Baker's Bay Golf & Ocean Club, the group took part as co-EPC partner in the design and construction of a 7 MW hybrid plant.

The plant combines three Jenbacher JMS420 engines with solar PV and a 3 MW / 3 MWh battery energy storage system (BESS). It is the direct precedent for GIS Power’s signature: solar and BESS as part of primary power.

Technical summary

  • 3 Jenbacher JMS420 engines
  • Solar PV
  • 3 MW / 3 MWh BESS
  • Project investment: USD 25 M
  • co-EPC partner