Projects · Querétaro, Mexico · 2013–2014
Alestra Green Data Center
The first data center powered by cogeneration in Mexico. The group designed, built and commissioned Alestra’s modular data center and the plant that supplies 100% of its power and chilled water.

4.2MW
Capacity
Querétaro, Mexico
2014
Year
2013–2014
400+GWh
Energy generated
Estimated to date
Full design and construction (EPC)
Scope
What was done
Alestra chose the group as its partner for a new data center in Querétaro: design, construction, fit-out and commissioning of a 35,000 m² modular facility, with 3,500 m² of white space in seven 500 m² modules.
The cogeneration plant, with two GE Jenbacher engines and two 350-ton absorption chillers, supplies the data center’s power and chilled water. The documented result was a 45% reduction in energy costs.
The project received DC Dynamics’ "Innovation in the Mega Data Center" award on October 1, 2014.
Technical summary
- 35,000 m² modular data center
- 3,500 m² of white space in 7 modules
- 2 GE Jenbacher engines
- 2 absorption chillers of 350 tons
- 100% of power and chilled water on site
- Project investment: USD 31 M
A similar project?